On November 3, 2026, voters in ten states decided 41 local ballot measures addressing data center development. In 40 of the 41 elections, voters approved measures that restrict or place conditions on data center development. Some measures also addressed the energy infrastructure that supports data centers, including battery storage and on-site natural gas generation. Only one pro-data center local ballot measure passed. Taken together, the results reflect strong community interest in how future data center projects are sited, powered, and integrated into local communities, and they highlight the value of early and sustained engagement with local stakeholders.

Twenty-one of the 41 ballot measures were in Ohio, more than any other state. The remainder were spread across California, Florida, Illinois, Kansas, Maine, Nevada, New Jersey, North Dakota, and Wisconsin. Most of the measures reached the ballot through citizen petitions rather than referral by local governments.

Below, we summarize the types of measures voters approved across four categories: (1) prohibitions on data center construction; (2) temporary moratoria; (3) requirements for a public vote before projects proceed; and (4) conditions on data center development. 

1. Prohibitions on Data Center Construction. Bans were the most common type of measure approved. Some prohibit data centers outright, while others apply only to facilities above a specified size or power threshold while continuing to permit smaller facilities. Eleven Ohio municipalities approved ballot measures that prohibit data center construction within their jurisdictions. Most of the measures define data centers as facilities that are “primarily or exclusively for digital information services such as the management, storage, processing and dissemination of electronic data and information,” although Urbana’s prohibition exempts data centers owned by and dedicated to a single enterprise with peak load below 7.5 megawatts. Many of the other prohibitions are limited to facilities with an aggregate monthly demand or peak load greater than 25 megawatts.

Outside Ohio, voters in Alhambra, California, Ottawa, Kansas, and Edgewater, Florida approved prohibitions on data center construction, while North Berwick, Maine prohibited data centers of 25,000 square feet or more. Emporia, Kansas and El Dorado, Kansas barred construction of both “High Impact Data Centers,” defined as facilities with peak electrical load above 10 megawatts or a daily water draw above 100,000 gallons, and certain battery energy storage systems.

2. Temporary Moratoria and Advisory Questions. Three Maine towns adopted temporary moratoria on data center development or permitting. Voters in six Illinois localities, Downe Township, New Jersey, and Monroeville, Ohio expressed either support for moratoria or opposition to permitting data centers in response to non-binding advisory questions on their ballots.

3. Public Vote Requirements.  Some measures conditioned development on public approval or certain commitments. Grove City, Ohio, now requires a public referendum for projects of 50 or more contiguous acres, 20 or more megawatts of peak electrical demand, or 500,000 or more gallons of water per day. Janesville, Wisconsin now requires a vote before the city leases, sells, transfers, or approves development of a specific site where project costs exceed $450 million. Where data centers remain a permitted use, these measures add a public approval step to the development process, making early and meaningful community engagement increasingly important.

4. Development and Financial Conditions. Perry, Ohio now requires hyperscale developers seeking tax abatements, PILOT programs, or other incentives to provide financial guarantees, including a bond backing promised jobs, payments to local services and community organizations, and tax revenue. Monroe and Sprigg Townships, Ohio established township zoning in unincorporated areas, giving local officials more control over siting major projects.

Reversal of Prior Local Government Approvals. Beyond these four categories, voters in several jurisdictions reversed decisions local governments had already made, including:

  • Wilmington, Ohio: In four separate referenda, voters rejected four ordinances that would have rezoned more than 545 acres from Rural Residential to Light Industrial and allowed development of data centers.
  • Ashville, Ohio: Voters rejected a resolution approving a development and supply term summary with a data center company. The deal covered two data center buildings and an associated natural gas “behind-the-meter” generating facility, meaning generation located on site that serves the facility directly rather than through the utility grid.
  • Boulder City, Nevada: Voters declined to make data centers an approved land use in the Eldorado Valley Transfer Area.

Looking Ahead

New state leadership. Voters also elected statewide officials who campaigned on additional oversight of data centers. Most notably, Democratic state Representative Gina Hinojosa defeated Governor Greg Abbott in the Texas gubernatorial election. During the campaign, Governor-elect Hinojosa said she would issue a moratorium on data center approvals until the Texas legislature enacts certain consumer and environmental protections, going beyond Governor Abbott’s current pause on grid connections and environmental permitting. Her stated priorities include requiring operators to pay for transmission, giving communities a voice, protecting ratepayers, screening for grid impacts, ending state tax incentives, restricting nondisclosure agreements, and requiring data center operators to hire union workers.

Federal permitting reform legislation. The Bipartisan American Affordability and Jobs Act (BAAJA) passed the Senate this month and awaits a final vote in the House. Among its many permitting and infrastructure-related provisions, BAAJA would require large data centers to bear the full incremental cost of the infrastructure built to serve them, an approach that could help address ratepayer concerns and support a clearer path forward for new projects. 

Companies investing in new data centers and associated power generation will need to navigate and monitor these shifting dynamics and benefit from engaging early with communities and policymakers at the state, local, and potentially federal levels. We will continue to closely track how state and local policymakers and regulators respond to both increased demand for new capacity and community input regarding new projects.